	<item>
		<title>Power Maintenance – Sunday 20th Dec 2009</title>
		<description>Coreix :: Power Maintenance – Sunday 20th Dec 2009
Location: STA.LON2

---------------------

The facility engineering team will be conducting power maintenance beginning at 02:00 GMT lasting until 06:00 on Sunday 20th Dec 2009.

Scope of work: Functional test of the new enhanced solution.

The commercial supply will be disconnected in a controlled manner by power ...</description>
		<link>http://status.coreix.net/2009/12/power-maintenance-%e2%80%93-sunday-20th-dec-2009/</link>
			</item>
	<item>
		<title>Power Maintenance – Sunday 6th Dec 2009</title>
		<description>Coreix :: Power Maintenance – Sunday 6th Dec 2009
Location: STA.LON2

---------------------

The facility engineering team will be conducting power maintenance beginning at 02:00 GMT lasting until 06:00 on Sunday 6th Dec 2009.

Scope of work: Functional test of the new equipment installed during the maintenance on the 4th Dec 2009.

The commercial supply will ...</description>
		<link>http://status.coreix.net/2009/12/power-maintenance-%e2%80%93-sunday-6th-dec-2009/</link>
			</item>
	<item>
		<title>Power Maintenance &#8211; Friday 4th Dec 2009</title>
		<description>Coreix :: Power Maintenance – Friday 4th Dec 2009
Location: STA.LON2

---------------------

The facility engineering team will be conducting power maintenance beginning at 03:00AM GMT on Friday 4th Dec 2009

Scope of work: Testing LV switch gear and failover from Primary to Backup power.
Outage: We do not anticipate any downtime during this testing.

Thank you ...</description>
		<link>http://status.coreix.net/2009/12/scheduled-maintenance-4th-dec-2009/</link>
			</item>
	<item>
		<title>Stratford Data Centre Update</title>
		<description>Our customers in the TATA Stratford, London facility have been directly affected by the power outage on Thursday 26th November 2009. During this period customers did not receive the normal level of service Coreix provides and we are working with TATA to ensure an incident of this magnitude does not ...</description>
		<link>http://status.coreix.net/2009/12/stratford-data-centre-update/</link>
			</item>
	<item>
		<title>Stratford Data Centre Incident Report</title>
		<description>Below is the incident report provided by TATA outlining the incident and the fix that has been put into place.




Date


Time in GMT


Details




26-Nov-09


16:45

Localized Power failure from Grid at Stratford IDC. The generator was kicked off to supply the power to the load.



26-Nov-09


17:00

The commercial power was restored and after a period of ...</description>
		<link>http://status.coreix.net/2009/12/stratford-data-centre-incident-report/</link>
			</item>
	<item>
		<title>Power Outage at TATA Stratford Facility</title>
		<description>At approximately 16:48 GMT the Stratford, London facility lost mains power from the power grid. The time-line of events is as follows:

16:48 - Power to site lost - running on UPS.
17:15 - UPS systems depleted, generators failed to start.
17:30 - Generators failovers failed to function despite multiple attempts - The ...</description>
		<link>http://status.coreix.net/2009/11/hello-world/</link>
			</item>