Emergency Maintenance – Service affecting connectivity between WGC & ENF
Scheduled Maintenance Report for Coreix
Completed
The scheduled maintenance has been completed.
Posted Sep 27, 2019 - 04:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 26, 2019 - 20:00 BST
Update
We will be undergoing scheduled maintenance during this time.
Posted Sep 25, 2019 - 14:23 BST
Scheduled
Coreix has received notification of maintenance from our connectivity provider (COLT) between Welwyn Garden City & Enfield Data Centre(s).
This is planned emergency maintenance that will take place over a period of no more than eight (8) hours, with an outage duration of no more than one (1) hour.
We are taking steps to minimise the impact upon services by re-routing traffic to our secondary link via Telehouse (WGC - THE - ENF) prior to the maintenance taking place.
We apologise for the inconvenience caused, but necessary maintenance is often unavoidable in the effort to be pro-active.
Should you experience any difficulties in this period the Support Team will be available by emailing support@coreix.net & creating a ticket.

We will update you upon completion of the task planned, marking this notification as "Resolved".
Posted Sep 25, 2019 - 14:22 BST
This scheduled maintenance affected: Networking (Metro Ethernet Service) and Facilities (DC1 - Enfield, DC2 - Welwyn Garden City).