Planned Network Maintenance affecting the Metro Network

Scheduled Maintenance Report for BE

Completed

The scheduled maintenance has been completed.
Posted Nov 30, 2019 - 06:00 GMT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 30, 2019 - 00:00 GMT

Scheduled

Coreix intends to carry out internal maintenance within its network.

The nature of the work is to finalise the exit from the London Hosting Centre site and as such remove all equipment from the network and that facility.

Customers within London Hosting Centre have already been contacted separately.

Whilst we do not anticipate any outages or issues during this period, customers on the Coreix metro network are considered at risk and may experience upto fifty (50) seconds of packet loss.

This will be solely restricted to Metro Circuits, whilst the Network converges.

Status updates are available at http://status.coreix.net

If you have any questions please contact support@coreix.net
Posted Nov 25, 2019 - 14:47 GMT
This scheduled maintenance affected: Facilities (Docklands) and Networking (Metro Ethernet Service).