Planned maintenance: Essential Network Element Maintenance - Welwyn Garden City Data Centre May 2nd 2024, (02/05/2024), 22.00hrs to May 3rd 2024, (03/05/2024) 04.00hrs GMT
Scheduled Maintenance Report for Coreix
Completed
This Planned Maintenance has been cancelled. Should this Planned Maintenance be rescheduled, we will notify you accordingly.
Posted Apr 19, 2024 - 11:51 BST
Scheduled
Coreix has received notification of maintenance that is service affecting the Welwyn Garden City Data Centre by our supplier COLT.

This is planned maintenance that will take place over a period of no more than six (6) hours, with an outage duration expected of no more than two hours (120 Minutes).

Link affected :

LE-611918

Coreix infrastructure, apart from that described above will not experience an outage and will not be at risk while the link described above is down.

The customer, that has services employing the transit link described above will be contacted directly.

If you have not been contacted directly to discuss this maintenance please ignore this notification.

We apologise for the inconvenience caused, but necessary maintenance is often unavoidable in an effort to be proactive.

Should you experience any difficulties in this period the Support Team will be available by emailing support@coreix.net .

In the interim, we will update you upon completion of the task planned, marking this notification as "Resolved" on the status page.
Posted Apr 12, 2024 - 16:21 BST
This scheduled maintenance affected: Networking (Metro Ethernet Service).