Essential Network Element Maintenance: Metro Network between Welwyn Garden City & Enfield Data Centre(s). September 11th 2025 (11/09/2025) 21.00hrs to September 12th 2025 (12/09/2025) 07.00hrs BST
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 11, 2025 - 21:00 BST
Scheduled
+be has received notification of maintenance affecting our Metro Network from our connectivity provider (COLT) between Welwyn Garden City, & Enfield Data Centre(s).
This is planned maintenance that will take place over a period of no more than ten (10) hours, with an outage duration of no more than ten (10) hours.
Links affected :
LE-256213-A
We are taking steps to minimise the impact upon services by re-routing traffic via alternative links, prior to the maintenance taking place. Returning the traffic to its original routing once completed.
+be infrastructure, apart from that described above, will not experience an outage and will not be at risk while the links described above are down.
The customer, who has services employing the transit link LE-256213-A will be contacted directly.
If you do not have Metro Services and have not been contacted directly to discuss this maintenance, please ignore this notification.
We apologise for the inconvenience caused, but necessary maintenance is often unavoidable in the effort to be proactive.
Should you experience any difficulties in this period, the Support Team will be available by emailing support.team@bec.uk & creating a ticket.
We will update you upon completion of the task planned, marking this notification as "Resolved" on the status page.
Posted Sep 09, 2025 - 08:32 BST
This scheduled maintenance affected: Networking (Metro Ethernet Service).