Planned Network Maintenance affecting a Lumen Circuit, Enfield Data Centre, September 13th 2023 (13/09/2023) 23.00hrs to September 14th 2023 (14/09/2023) 02.00hrs
Scheduled Maintenance Report for Coreix
Completed
The scheduled maintenance has been completed.
Posted Sep 14, 2023 - 02:01 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 13, 2023 - 23:00 BST
Scheduled
Coreix has received notification of maintenance affecting a Transit Circuit from our connectivity provider Lumen from our Welwyn Garden City Data Centre.

This is planned maintenance that will take place over a period of no more than three (3) hours, with an outage duration of no more than one (1) hour.

Links affected: 441748278 & 441748277


Coreix infrastructure, apart from that described above will not experience an outage and will not be at risk while the circuit described above is down. Any traffic via this transit circuit will be re-routed via an alternative transit circuit, prior to the maintenance taking place.

No impact upon services is expected.

We apologise for the inconvenience caused, but necessary maintenance is often unavoidable in an effort to be proactive.

Should you experience any difficulties in this period the Support Team will be available by emailing support@coreix.net .

In the interim, we will update you upon completion of the task planned, marking this notification as "Resolved" on the status page.
Posted Aug 31, 2023 - 16:25 BST
This scheduled maintenance affected: Networking (IP Transit, Metro Ethernet Service).